Kitchen floor rebuilt before a one-week reopening — in normal hours, at lower cost

What started as a list of kitchen repairs revealed a failed sub-floor. We recommended a full replacement, brought the work forward into the closure and finished before the doors opened.

Restaurants & pubsCommercial flooringCommercial kitchensPlanned repairs
New Altro safety flooring with cap-and-cove skirting in a commercial kitchen

Background

The restaurant was closed for a week of maintenance ahead of reopening. Multiple kitchen repairs were scheduled.

The challenge

Inspection showed the sub-floor had deteriorated beyond patch repair. A full replacement had to be sourced, programmed and completed inside the remaining closure — or the reopening would slip.

What we did

  1. 1Advised full floor replacement and re-sequenced the programme to complete it during the closure rather than in out-of-hours shifts.
  2. 2Procurement team sourced additional levelling compound at short notice.
  3. 3Stripped defective Altro and skirting, applied latex screed, fitted cap-and-cove and new Altro safety flooring with welded seams.
  4. 4Reinstated and reconnected kitchen equipment ready for reopening.

Results

  • Before reopeningDelivered inside the closure window
  • Normal hoursNo out-of-hours premiums
  • Lower costVersus phased night-time works

More client stories

Have a similar problem?

Full Altro floor replaced and kitchen recommissioned before reopening, without out-of-hours premiums.