Background
The riser was fully enclosed with no access panels, so the leaks could neither be inspected nor repaired.
The challenge
Water damage across five floors, an inaccessible riser, and a specialist contractor who needed safe access to work.
What we did
- 1Joint survey with Metro Mechanical to locate each failure.
- 2Formed access openings floor by floor so the drainage specialist could carry out repairs.
- 3Repaired walls and ceilings and replaced carpets once the pipework was signed off.
Results
- 5 floors — Returned to use
- 1 team — Coordinating access, repair and reinstatement